Let's summarize what's occured so far in the process:
Framing is complete
Plumbing rough-in is complete
A/C is complete (can't turn it on until the inspection)
Electrical rough-in is complete
Inspection Schedule (Set for tomorrow 1/16):
Plumbing underground inspection (since we moved the toilet and drain) *Complete*
Plumbing rough-in
Electrical rough-in
Framing
A/C (I think this is the same inspector as electrical but may be a seperate inspection report)
Work scheduled for today:
Bill will be out to do required caulking and foam for fire blocking.
Plumber will be out to set the pan for the shower so he can pass rough-in, although the bathroom tile guy will replace it later in the process. This is to ensure there's no leaks created by people working.